ResMed
Challenge
At 99.9% completion, it was brought to our attention by our main material supplier that the product they had supplied on the project was not Fire Code compliant. This required Division 8 to remove and reinstall 100% of the Rainscreen panel system in about 1/8 of the originally allotted schedule timeframe.Solution
By mobilizing our expert team of panel fabricators and installers, Division 8 was able to provide the required R & R, and deliver the completed scope of work within the General Contractor's original schedule date.Expertise
Composite PanelsRainscreen Systems